Minas-Rio: an iron ore operation in Brazil
Minas-Rio is an integrated mine and processing complex producing iron ore in Minas Gerais, Brazil, with a 529 km slurry pipeline to the Port of Acu, Brazil, operated by Anglo American. The sources report 24,752 thousand tonnes ('000 t), pellet feed, wet metric tonnes for CY2025; the basis is 100% of the operation (Anglo American consolidates Minas-Rio), as reported by the owner. Measured as usable ore, whole-operation output for CY2025 is 24,752,000 tonnes: about 1% of world iron ore output in 2025 and about 5.9% of Brazil's; it is one of 21 operations on this site whose output can be stated in usable ore.
Who owns and operates it?
| Owner | Interest | As of |
|---|---|---|
| Anglo American | 85% | 31 December 2025 |
| Vale | 15% | 31 December 2025 |
How much does it produce?
| Period | Output | Basis | Where in the source |
|---|---|---|---|
| CY2025 | 24,752 thousand tonnes ('000 t), pellet feed, wet metric tonnes | 100% of the operation (Anglo American consolidates Minas-Rio), as reported by the owner | printed p.8, Premium iron ore table, row 'Minas-Rio - Brazil'; printed p.9, row 'Pellet feed' under Minas-Rio production, 2025 column · Anglo American plc |
| CY2024 | 25,037 thousand tonnes ('000 t), pellet feed, wet metric tonnes | 100% of the operation, as reported by the owner | printed p.8, same row, 2024 column · Anglo American plc |
Between CY2024 and CY2025 the reported figure fell by 1.1%, in the same unit and on the same basis.
How the usable-ore figure is worked out. Anglo American prints 24,752 thousand wet metric tonnes of pellet feed produced at Minas-Rio in 2025. The report states volumes at wet basis and the table is not labelled as a share; Anglo American holds 85%, so the figure is read as the whole-operation total reported by the majority owner. World mine production of usable ore in 2025 was 2,600,000,000 tonnes (USGS Mineral Commodity Summaries 2026); Brazil produced 420,000,000 tonnes.
Of the 21 iron ore operations on this site with a stated usable-ore figure, Minas-Rio ranks 15th by whole-operation output. The largest, Western Australia Iron Ore (WAIO), is 291,164,000 tonnes; Minas-Rio is 8.5% of that. Periods and bases differ between operators, so the ranking is indicative.
Status: operating, as of 31 December 2025.
- Anglo American reports Minas-Rio as a single product, pellet feed, in wet metric tonnes; the product is shipped with about 9% moisture (printed p.8).
- Anglo American says it announced in February 2024 an agreement to acquire and integrate the contiguous Serpentina resource into Minas-Rio (annual report, footnote 12).
How does it compare?
The 7 iron ore operations on this site closest to Minas-Rio in whole-operation output, as stated by each operator (periods and bases differ, so the order is indicative):
| Rank | Operation | Country | Output (tonnes of usable-ore) | Operator |
|---|---|---|---|---|
| 12 | Mariana complex | Brazil | 28,400,000 | Vale |
| 13 | Sishen | South Africa | 25,289,000 | Kumba |
| 14 | Itabira complex | Brazil | 25,200,000 | Vale |
| 15 | Minas-Rio | Brazil | 24,752,000 | Anglo American |
| 16 | Iron Ore Company of Canada (IOC) | Canada | 15,905,000 | Rio Tinto |
| 17 | Donimalai Iron Ore Complex (Donimalai and Kumaraswamy pits) | India | 15,600,000 | NMDC |
| 18 | Paraopeba complex | Brazil | 15,000,000 | Vale |
In Brazil: Serra Sul (S11D), Carajas, Serra Norte, Carajas, Itabira complex, Minas Centrais complex, Mariana complex and 3 more. See where iron ore comes from for the country totals, the country page for Brazil, and Anglo American for its other operations here.
Sources
- Anglo American plc: Integrated Annual Report 2025 (annual report, CY2025). Opened 4 November 2026; used: PDF pp.17, 48, 138, 141; also PDF pp.160, 323.
- Anglo American plc: Production Report for the fourth quarter ended 31 December 2025 (quarterly production report (RNS, 5 February 2026), Q4 2025 and CY2025). Opened 4 November 2026; used: printed pp.8-9 (Premium Iron Ore).
- U.S. Geological Survey: Mineral Commodity Summaries 2026: Iron Ore (government statistical summary, 2025 (world and country mine production of usable ore)). Opened 3 November 2026; used: world and country mine production table, usable ore.
Method and limits
- What is compared. Operators print tonnes of ore: saleable production for most, run-of-mine and pelletizing feed for Vale, and shipments for Fortescue and Onslow Iron, mostly as wet tonnes. The figure is compared with the USGS usable-ore total, which does not state a moisture basis, so the share is indicative.
- Output is reported by the operator or owner, never estimated here; the basis column says whether a figure is the whole operation or an owner's share. The general rules for shares, partial lists and basis are on the methodology page.
- Made with AI assistance and checked against the documents above (how the site is made). To report an error, contact us; fixes are logged on the corrections page.